CriterioPublic information, explained
Menu ES

“RECONSTRUCCIÓN DE LA CARRETERA DE PEDERNALES – PUERTO ESCONDIDO – DUVERGE, PROV. PEDERNALES E INDEPENDENCIA”

Figures are live. Official names, document titles and new text may stay in Spanish.

Ministerio de Obras Públicas y Comunicaciones contracted Consorcio Avance del Sur por RD$3,342,769,322.00.

Documented · Source: DGCP, open data · checked automatically every 12 hours

ItemValue
InstitutionMinisterio de Obras Públicas y Comunicaciones
SupplierConsorcio Avance del Sur
Monto contratadoRD$3,342,769,322.00
StatusActive
CodeMOPC-2026-00313
ProcessMOPC-CCC-LPN-2026-0012
Procurement methodNational public tender
ExceptionProceso ordinario
Estimated amount of the processRD$3,714,219,152.89
Contract term12dias
SNIP code—
The companyConsorcio, proveedora del Estado desde el 10 de agosto de 2026. No clasificada
Official recordOpen in Compras Dominicana

Timeline

  1. The process was published
  2. Amendment date of the process
  3. Bid deadline
  4. Expected award
  5. Award
  6. The contract was registered

What was bought

ItemQuantityUnit priceTotal
RECONSTRUCCIÓN DE LA CARRETERA DE PEDERNALES – PUERTO ESCONDIDO – DUVERGE, PROV. PEDERNALES E INDEPENDENCIA1 unit(s)RD$3,237,273,999.81RD$3,342,769,322.25

Registered bids (4)

The amount is the whole bid's; a contract may cover only part of it.

Original documents

9 documentos en el portal oficial. Por su nombre, no vemos: Acta de adjudicación, Contrato firmado, Informe de evaluación. Pueden estar con otro nombre.

What we do not know