Ampliación del Plantel Educativo para Inicial Bejucal, Municipio Higüey, Provincia la Altagracia.

2026 budget, execution as of 13 November · Documented

Initial budget1.2RD$ M
Current budget1.8change +0.6
Accrued1.480.0% of current

What the file says: 80.0% of the 2026 current budget accrued.

Where and funded by what

ProvinceSourceInitialCurrentAccrued
La AltagraciaGeneral Fund1.21.81.4

Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget