CriterioPublic information, explained
ES

← All projects

Ampliación del Plantel Educativo para Inicial Prof. Felipe Jiménez Peña, Municipio Bonao, Provincia Monseñor Nouel.

2026 budget, execution as of 13 November · Documented

Initial budget1.5RD$ M
Current budget4.5change +2.9
Accrued4.5100.0% of current

What the file says: The 2026 current budget is fully accrued.

Where and funded by what

ProvinceSourceInitialCurrentAccrued
Monseñor NouelGeneral Fund1.54.54.5

Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget