CriterioPublic information, explained
ES

← All projects

Ampliación del Plantel Educativo para Inicial Luis Ramírez Mora, Municipio Tábara Arriba, Provincia Azua.

2026 budget, execution as of 13 November · Documented

Initial budget2.5RD$ M
Current budget4.0change +1.5
Accrued3.176.8% of current

What the file says: 76.8% of the 2026 current budget accrued.

Where and funded by what

ProvinceSourceInitialCurrentAccrued
AzuaGeneral Fund2.54.03.1

Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget