Reconstrucción Puente Mixto en la Carretera la Descubierta - Boca de Cachón, Provincia Independencia

2026 budget, execution as of 13 November · Documented

Initial budget44.5RD$ M
Current budget0.5change −44.0
Accrued0.00.0% of current

What the file says: No accrued spending recorded as of 13 November 2026.

Where and funded by what

ProvinceSourceInitialCurrentAccrued
IndependenciaGeneral Fund44.50.50.0

Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget