Construcción Nuevo Puente de Alcantarilla de Cajon Sobre Arroyo Caguero por Daños Vaguada Abril 2022, Municipio Higuey, Provincia la Altagracia

2026 budget, execution as of 13 November · Documented

Initial budget15.0RD$ M
Current budget15.0change +0.0
Accrued15.0100.0% of current

What the file says: The 2026 current budget is fully accrued.

Where and funded by what

ProvinceSourceInitialCurrentAccrued
La AltagraciaGeneral Fund15.015.015.0

Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget