Ampliación del Plantel Educativo para Inicial Colombina Castro, Municipio Boca Chica, Provincia Santo Domingo.

2026 budget, execution as of 13 November · Documented

Initial budget0.0RD$ M
Current budget2.3change +2.3
Accrued2.187.3% of current

What the file says: 87.3% of the 2026 current budget accrued.

Where and funded by what

ProvinceSourceInitialCurrentAccrued
Santo DomingoGeneral Fund0.02.32.1

Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget