Reconstrucción de la Infraestructura Vial Urbana del Municipio las Salinas, Provincia Barahona

2026 budget, execution as of 13 November · Documented

Initial budget5.1RD$ M
Current budget5.1change +0.0
Accrued5.199.0% of current

What the file says: 99.0% of the 2026 current budget accrued.

Where and funded by what

ProvinceSourceInitialCurrentAccrued
BarahonaGeneral Fund5.15.15.1

Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget