Construcción Línea 2c del Metro de Santo Domingo Tramos: Alcarrizos- Luperón
Initial budget4,820.0RD$ M
Current budget4,781.8change −38.2
Accrued3,751.778.5% of current
What the file says: 78.5% of the 2026 current budget accrued.
Where and funded by what
| Province | Source | Initial | Current | Accrued |
|---|---|---|---|---|
| Santo Domingo | External credit | 2,620.0 | 2,681.8 | 1,822.4 |
| Santo Domingo | Domestic credit | 1,500.0 | 1,500.0 | 1,398.6 |
| Santo Domingo | General Fund | 700.0 | 600.0 | 530.7 |
Source: DIGEPRES, weekly execution report · retrieved November 23, 2026 · See the 2026 budget